The SEI audits a sample of CMMI High Maturity appraisals. The following are the
criteria being used for these audits. These criteria in no way limit
the application of the model or its intent or judgments made during an
appraisal, nor do they relieve the organization from fully implementing
the model.
Organizational Process Performance
- (SP 1.1) Show the relationship between the business objectives and the processes selected for process performance analysis.
- (SP 1.2) Show the analysis and rationale for deciding what data to include in the process performance analysis.
- (SP 1.3) Show the relationship between business objectives and Quality and Process Performance Objectives (QPPOs).
- (SP 1.4) Describe Process Performance Baselines (PPBs) in terms of
central tendencies and variation for the processes selected for
analysis.
- (SP 1.5) Describe at least one Process Performance Model (PPM) in
terms of the processes included, the controllable inputs and the
predicted outputs. The model must be statistical or probabilistic in
nature rather than deterministic, i.e., the model considers uncertainty
and predicts that uncertainty or range of values in the outcome.
Quantitative Project Management
- (SP 1.2) Describe how the projects created their defined process by
using PPBs and/or PPMs to predict the ability of the processes selected
to meet the project’s QPPOs.
- (SP 1.3) Describe the project’s rationale for selecting subprocesses to be statistically managed.
- (SP 1.4) Show how at least one project used process measures as inputs to a PPM used to actively manage the project.
- (SP 2.2) Show that at least one project applied statistical methods
to identify and remove special causes of variation from selected
subprocesses.
- (SP 2.3) Show how projects monitor the capability of selected subprocesses.
Causal Analysis and Resolution
- (SP 1.2) Demonstrate that at least one of the defects or problems
selected for analysis was related to a quantitatively managed process,
where “quantitatively managed” is as defined in the glossary.
Organizational Innovation & Deployment
- (SP 2.3) Demonstrate that the effects of at least one improvement were measured for statistical significance.
As defined in the SCAMPI v1.2 Method Definition Document Section
1.1.3, these criteria refer to the instantiations in the representative
sample that are identified as either focus projects, non-focus
projects, or other organizational level instantiations with a scope