Teradyne Results Using PSP and TSP

The first organization to report their results after using both PSP and TSP was Teradyne. Their return on investment (ROI) analysis indicates that by using PSP and TSP on two projects totaling 112 KLOC, they saved $5.3 million in engineering time, or approximately 120 hours/KLOC in integration, system, and field testing. Quality levels improved 20 times over prior projects and actual effort and schedule were within 8% of plan (early). Teradyne estimates the cost of PSP training to be one month per engineer. Below are specific details about one of Teradyne's projects.

Project

Plan

Actual

Size

110,000 LOC

89,995 LOC

Effort

16,000 hours

14,711 hours

Schedule

77 weeks

77 weeks

 

Product Quality (defects/KLOC removed in phase)

Project

Plan

Actual

Integration

1 Defect/KLOC

0.2 Defect/KLOC

System test

0.1 Defect/KLOC

0.4 Defect/KLOC

Field trial

0 Defect/KLOC

0.02 Defect/KLOC

Operation

0 Defect/KLOC

N/A


For More Information