Case Study: Significant Schedule Delays in a Complex NDI-Based System

SEI Report
The expected audience for this monograph is a general audience, and the major issues tend to be more programmatic and managerial rather than purely technical.
Publisher

Software Engineering Institute

Topic or Tag

Abstract

This monograph describes a program that is currently building a large system for the DoD. This system makes extensive use of pre-existing components: re-engineered legacy systems, components that are government-furnished equipment (GFE), and both government- and commercial-off-the shelf (GOTS and COTS) software. Thus, although the system is not precisely a "COTS-based system," the issues faced in building this system are parallel enough to those in COTS-based systems to make it a useful case study.

The expected audience for this monograph is a general audience, and the major issues tend to be more programmatic and managerial rather than purely technical. The goal of the monograph is to focus on the complexities (which do include both technical and programmatic issues) that can hinder or dilute the expected benefits of using commercial components in complex government systems.

Cite This SEI Report

Carney, D. (1998, June 1). Case Study: Significant Schedule Delays in a Complex NDI-Based System. Retrieved August 12, 2026, from https://www.sei.cmu.edu/library/case-study-significant-schedule-delays-in-a-complex-ndi-based-system/.

@techreport{carney_1998,
author={Carney, David},
title={Case Study: Significant Schedule Delays in a Complex NDI-Based System},
month={Jun},
year={1998},
institution={Software Engineering Institute, Carnegie Mellon University},
url={https://www.sei.cmu.edu/library/case-study-significant-schedule-delays-in-a-complex-ndi-based-system/},
note={Accessed: 2026-Aug-12}
}

Carney, David. "Case Study: Significant Schedule Delays in a Complex NDI-Based System." Software Engineering Institute, Carnegie Mellon University. Software Engineering Institute, June 1, 1998. https://www.sei.cmu.edu/library/case-study-significant-schedule-delays-in-a-complex-ndi-based-system/.

D. Carney, "Case Study: Significant Schedule Delays in a Complex NDI-Based System," Software Engineering Institute, Carnegie Mellon University. Software Engineering Institute, 1-Jun-1998 [Online]. Available: https://www.sei.cmu.edu/library/case-study-significant-schedule-delays-in-a-complex-ndi-based-system/. [Accessed: 12-Aug-2026].

Carney, David. "Case Study: Significant Schedule Delays in a Complex NDI-Based System." Software Engineering Institute, Carnegie Mellon University, Software Engineering Institute, 1 Jun. 1998. https://www.sei.cmu.edu/library/case-study-significant-schedule-delays-in-a-complex-ndi-based-system/. Accessed 12 Aug. 2026.

Carney, David. Case Study: Significant Schedule Delays in a Complex NDI-Based System. Software Engineering Institute. 1998. https://www.sei.cmu.edu/library/case-study-significant-schedule-delays-in-a-complex-ndi-based-system/